Our company Rudarmin Engineering DOOEL Export – Import Skopje, has successfully completed the following projects in the period 2017 – 2020.

For the client – investor MAKALJB KOMPANI DOO Skopje, we have successfully completed the following projects in the period 2017 – 2020:

  • Contract for performing drilling works concluded on 07.11.2017. For the exploitation of stone from the Dobarski Zeden Quarry, municipality of Zelino in the immediate vicinity of the village Grupchin.
  • Active contract for performing drilling – mining works concluded on 20.08.2020. At the Dobarski Zeden Quarry, municipality of Zelino near the village of Grupchin.

For the client – investor AKTUEL ENERGY GROUP DOO Skopje, we have successfully completed the following projects in the period 2016 – 2019:

  • Contract for performing of drilling and mining works concluded on 16.08.2016, i.e. for individual drilling works on material – raw material (rock) and crushing of flocs on the same for the needs of the client, for the realization of construction of Small Hydro Power Plant KOVACHKA with ref. .no.21 in KO Samokov, municipality of Makedonski Brod.
  • Agreement for mutual cooperation concluded on 05.07.2017. or performing mining-drilling works for the needs of the client-investor.

For the client – investor CEACON DOOEL Tetovo, we have successfully completed the following project in 2017

  • Contract for performing mining works, concluded on 16.08.2017. The subject of this contract is a service of mining works for the needs of the Investor for the realization of the construction of a small hydro power plant MHE Gabrovska river with ref. No. 104 in the Municipality of Tearce.

For the client – investor STONE MINERALI DOO Tetovo, we have successfully completed the following project in 2017 and 2018

  • Contract for performing drilling – mining works concluded on 06.10.2017. The subject of this contract is a service of drilling and mining works for the needs of the client or investor, for the exploitation of non-mineral resources at Kamenolom Voda near the village of Cegrane, Gostivar.

For client – investor MIRSAT KOMERC import-export Zeqir Zeqirovski, we have successfully completed the following projects in the period 2017 – 2020,

  • Contract for performing of drilling – mining works concluded on 16.10.2017. The subject of this contract are drilling and mining works for drilling a road in the immediate vicinity of Makedonski Brod.
  • Contract for performance of drilling works concluded on 20.07.2020. The subject of this contract is a service for drilling works for installation of anchors for slopes stability of cuttings and side cuts on the Highway Kicevo – Ohrid.

For client – investor GEOING MK DOO Skopje, we have successfully completed the following project in 2017

  • Agreement for performance of drilling – mining works concluded on 30.10.2017. Subject of the contract is business cooperation between the contracting parties for performing all drilling and mining works.

For client – investor PETROS DOO Kumanovo, we have successfully completed the following project in 2017 and 2018

  • Contract for performing of drilling and mining works concluded on 28.11.2017. At the Quarry from the deposit Crkoven Rid, village Orasec, municipality of Kumanovo.

For client – investor EURO JANI KOP import – export DOO village Suvodol, Makedonski Brod, we have we have successfully completed the following projects in the period 2017 – 2019

  • Contract for performing of drilling and mining works, concluded on 20.12.2017, on the locality Ogledalec, municipality of Makedonski Brod.
  • Annex for extension of the contract until 06.09.2019.

For client – investor ENGINEERING TERAKOTA import – export doo Prilep, we have we have successfully completed the following projects in the period 2018 – 2020

  • Contract for performing of drilling and mining works, concluded on 19.02.2018 at the locality Quarry Sladun, near the village Trojaci.
  • Annex for extension of the contract until 19.02.2019.
  • Annex No. 1 for extension of the contract until 18.02.2020.
  • Annex no. 2 for extension of the contract until 18.02.2021.

For client – investor KONDRI ENGINEERING Urim Kondri DOOEL Veleshta, we have successfully completed the following project in the period 2018 – 2019

  • Contract for performing of drilling and mining works concluded on April 18, 2018, for the exploitation of limestone at the locality Dolna Krasta in the area of the village Velesta, Struga region.

For client – investor RENOVA DОО export – import village Dzepcishte, Tetovo, we have successfully completed the following project in the period 2018 – 2019

  • Contract for performing of drilling and mining works concluded on June 20, 2018. for Locality Roshje, village Brnik, municipality of Novaci.

For client – investor PELA TRANS DООЕL village Mazhucishte, Prilep, we have successfully completed the following projects in the period 2018 – 2020

  • Contract for performing of drilling and mining works concluded on 20.06.2018 at the locality Papradishte, village Dragov Dol municipality of Makedonski Brod.
  • Contract for performing of drilling and mining works concluded on 17.07.2019 at the locality Papradishte, village Dragov Dol municipality of Makedonski Brod.

For client – investor VOLOSTONE DОО Skopje, we have successfully completed the following project in the period 2018 – 2019

  • Contract for performing of mining works, concluded on 18.09.2019. at the locality Samarnica.

For client – investor OGRAZHDEN AD Strumica, we have successfully completed the following projects in the period 2018 – 2020

  • Contract for performing mining works concluded on 20.09.2018, at the sites – surface mines of Quarry Hamzali (mineral raw material feldspar) and Quarry Memeshli (mineral raw material marbled limestone).
  • Contract for performing mining works concluded on 09.11.2020, at the sites – surface mines of Quarry Hamzali (mineral raw material feldspar) and Quarry Memeshli (mineral raw material marbled limestone).

For client – investor SOPOT DОО export – import Skopje, we have successfully completed the following projects in the period 2018 – 2020

  • Contract for performing drilling works concluded on 20.09.2018. for exploitation of a stone from Quarry Sopot, village Sopot, municipality of Kumanovo.

For client – investor HABI GRADBA import – export DOOEL Makedonski Brod, we have successfully completed the following project in the period 2018 – 2020

  • Contract for performing of mining works concluded on March 23, 2018, at the site of Quarry Dolgi Rid.
  • 2) Annex No. 1 for extension of the contract until 24.03.2020.

For client – investor PELA TRANSPORT DOOEL Skopje, we have successfully completed the following project in the period 2019 – 2020

  • Contract for performing of drilling and mining works concluded on March 25, 2019 on the Express Road Section Kriva Palanka – Dlabochica.

For client – investor TETA – KOP DOOEL Veles, Велес, we have successfully completed the following project in the period 2019 – 2020

  • Contract for service of a construction machine concluded on 22.05.2019. Subject of this contract is performance of drilling works at Quarry Sopot, village Sopot, municipality of Kumanovo.

For client – investor PROMING DOOEL export – import Struga, we have successfully completed the following project in the period 2019 – 2020

  • Contract for performing of drilling – mining works concluded on 15.10.2019, on the site Modric.

For client – investor ZAGRACHANI KOMERC import – export DOOEL Struga, we have successfully completed the following project in the period 2019 – 2020

  • Contract for performing of drilling and mining works concluded on 28.10.2019. at the locality Babush.

For client – investor JES GLOBAL DOOEL export – import Skopje, we have successfully completed the following projects in the period 2019 – 2020

  • Contract for performing of drilling and mining works concluded on 01.11.2019. for connected dual system 110 KV transmission line for Transformer Station (TS) Neokazi by cutting the existing 110 KV transmission line TS Stip – TS Probistip.
  • Contract for performing of drilling and mining works concluded on 02.04.2020, on the state road A-2 Rankovce – Kriva Palanka.
  • Contract for use of geodetic and other consulting services on 01.03.2020, for operation of the following projects:
    • Express way Section Rankovce – Kriva Palanka, selection junction Kriva Palanka – Dlabochica km. 0 + 000 – 1+ 424 L = 1.42 km (per ramp)
    • Express way Section Rankovce – Kriva Palanka section junction Kriva Palanka – Dlabochica (from profile 256+ to profile 281).

For client – investor LOIS GEMSTONE DООЕL import – export Kicevo, we have successfully completed the following project in 2019

  • Contract for performing of drilling and mining works concluded on 03.03.2020. at Quarry Izvor near the village Izvor, Kicevo.

For client – investor ILINDEN AD Struga, we have successfully completed the following projects in 2020

  • Contract for performance of drilling works concluded on 05.04.2020. on the Highway Kicevo – Ohrid.
  • Contract for performance of drilling works concluded on 23.09.2020. on the highway Kicevo – Ohrid, construction site Preseka.

For client – investor GEOTEHNIKA DOOEL Stip, ООЕЛ Штип, we have successfully completed the following projects in 2020

  • Contract for performing of drilling and mining works concluded on April 30, 2020. at the Quarry Ezhovo Brdo Stip.
  • Contract for performing of drilling and mining works concluded on 21.05.2020 at the Kamen Dol quarry, village Kamen Dol near the village Rosoman Kavadarci.

For client – investor BETON AD Skopje, we have successfully completed the following projects in 2020

  • Contract for drilling and blasting for construction of foundations of Viaduct 8 and Viaduct 10 concluded on 06.10.2020, for the construction of the expressway A2 section Interchange Kriva Palanka – Dlabochica.
  • Contract for performing of drilling and mining works concluded on 03.02.2020, on the Highway Section Stip – Kocani (near the village Krupishte).

For client – investor EXPLOTEC MAC DООЕL Radovish, we have successfully completed the following project in 2020

  • Business cooperation agreement, concluded on 10.12.2019. for performing drilling works with a hydraulic drilling machine for drilling deep mine holes for the needs of the investor.